- The 60% CIL facility expansion has seen increased production of gold from 500 to 800 tonnes per day. Work on the additional Sokor underground gold mining facility is underway and is expected to be completed by 1H26. We believe management is keen to increase shareholder returns through dividends if earnings exceed expectations.
- - Read this at SGinvestors.io -
Key Highlights
Increased daily throughput capacity from 500 to 800 tonnes per day
- The completed 60% CIL plant expansion has successfully increased daily throughput capacity from 500 to 800 tonnes per day. Operations are running at full expanded capacity with production continuity materially improved. The expanded configuration allows uninterrupted processing even during maintenance or unexpected downtime in any of the processing circuits due to the dual circuit system.
- - Read this at SGinvestors.io -
Development of the additional Sokor underground mining facility is progressing